|
BY KABURU MUGAMBI
East Africa Portland
Cement Company has readvertised the
tender for a new cement mill that
was cancelled by the Government in
January citing “serious flaws” in
the procurement process.
The tender for design,
supply and installation of a new 60-tonne-per-hour
cement milling facility at its Athi
River plant closes on April 26, 2006.
In an interview, Managing Director
Ole Mapelu Zakayo said the cancellation
of the tender means the project would
fall two months behind schedule.
The Government’s
action had put in jeopardy the company’s
contract to supply more than a million
tonnes of cement to Southern Sudan.
“Although we have
lost the months, we are not very far
behind and we believe in the next
15 months the new mill will be up
and running in time to tap into the
new markets, especially Sudan, he
said. The new facility will ensure
the company meets the needs of a growing
market while considerably lowering
its energy and production costs.
Portland says bidders
must be established cement technology
holders, who are manufacturers and
suppliers of main cement production
equipment and must have done similar
installations in the past five years.
The contractors to be used for the
erection must have experience in industrial
installations of similar magnitude.
All tenders must
be accompanied by a $750,000 (Sh54.2
million) tender security. On what
went wrong in the first tender which
was cancelled, Mr Mapelu said: “Our
procurement process is very elaborate,
with Treasury participation, but in
this case we could have forgotten
about little details, for instance,
not sending letters in time.”
The Public Procurement
Complaints Committee and Appeals Board
cancelled the tender award to KMPP
Polysius of South Africa, citing irregularities
in the tendering process. The board
said the laid down rules on procurement
and public tendering were not correctly
followed. Other companies that bid
for the contract were Imasa Ingeniena
Montajes – the highest bidder at Sh1.8
billion – KMPP Polysius of South Africa
at Sh1.1 billion, SPM Engineers India,
which bid at Sh857 million and FL
Smith A/S Denmark, the lowest at Sh737
million. New Barnon & Leveque
International bid at Sh2.1 billion.
New Baron &
Leveque, FL Smith and Polysius met
all the criteria, while the other
two were disqualified on technicalities.
The tender committee accepted Polysius’s
bid, which was also ratified by the
Portland’s board. The tender was cancelled
following an appeal by New Baron &
Leveque International, one of the
shortlisted bidders, which claimed
that new criteria were introduced
at the evaluation stage, hence disadvantaging
some tenderers.
Leveque said that
between September and October last
year, members of the technical and
financial evaluation committee visited
the countries of operation of the
three shortlisted bidders.
After the visit,
the three submitted revised prices
and specifications, which was done
orally in breach of the tendering
regulations. The new prices quoted
after the visits increased by between
Sh300 million and Sh500 million Leveque
said in the appeal.
These visits were
done after the tender opening on June
15,2005, while the evaluation process
was in progress,” the board said in
its ruling. “We have also noted that
the successful tenderer did not have
the lowest prices in both instances;
at the tender opening stage and at
the financial evaluation stage.”
Last year, demand
for cement went up by 15 per cent
compared to the previous year, following
increased orders from the construction
industry.
The turnover
rose from Sh2.5 billion to Sh3.1 billion.
“The company is faced with a rapidly
increasing demand and the challenge
is how to increase its capacity,”
Mr Mapelu said.
|